5.2 Installation of Tramcar Dumper
General Items
5.2.1 The allowable deviation for installation of tramcar dumper shall be in accordance with those specified in Table 5.2.1.
Inspection quantity:exhaustive check.
Inspection method:see Table 5.2.1.
Table 5.2.1 Allowable deviation for installation of tramcar dumper


Figure 5.2.1-1 Tramcar dumper installation diagram
1-Rotator;2-Top stopper;3-Rail;4-Support roll;5-Base;6-Positioner;7-Drive roller

Figure 5.2.1-2 Rotator assembling

Figure 5.2.1-3 Positioning pin
1-End disc;2-Buffer;3-Positioning pin